As we head into the home stretch of 2022, there is lots of exciting headway continuing on our ten developments currently under construction across South East Queensland, with Mosaic Construction gearing up to complete two new luxury addresses in early 2023.

Kensington by Mosaic | Toowong

Address: 36 Sylvan Road, Toowong

Apartments: 63

Builder: Mosaic Construction

Sales Status: Sold out

Mosaic Construction continues to hit exciting milestones, having now completed the level 6 concrete slab pour. Weather permitting, September will see the team complete the level 8 slab, meaning we are very close to building top out! Internal works continue with the installation of window frames and glazing as well as services rough in. Joinery will also commence this month.

CLICK TO LEARN MORE ABOUT KENSINGTON

Lorient by Mosaic | Maroochydore

Address: 88 Duporth Ave, Maroochydore

Apartments: An ultra-luxury collection of 15 half and full-floor penthouse-style residences.

Builder: Mosaic Construction

Sales Status: Sold out

Exciting progress this month with bulk excavation complete and shotcrete applied to the basement retention walls. Lorient’s tower crane has also been installed, and prep work is underway for the basement slab pour, which, all going to plan, will take place this month.

CLICK TO LEARN MORE ABOUT LORIENT

Luca by Mosaic | Kirra

Address: 7 Douglas Street, Kirra

Apartments: 31

Builder: Mosaic Construction

Sales Status: 90% Sold

Demolition of the existing structures and site clearing is now complete. Everything is tracking as it should be behind the scenes, with Mosaic Construction finalising all required trades and approvals to commence Luca’s initial site excavation activities, with piling as the first activity.

CLICK TO LEARN MORE ABOUT LUCA

The Patterson by Mosaic | Toowong

Address: 15 Archer Street, Toowong

Apartments: 66

Builder: Mosaic Construction

Sales Status: Sold out

The excitement continues this month as we are one slab closer to building top out! With the level 14 slab complete, formwork and verticals are progressing to level 15. Internally, services rough-in is progressing to level 11, with plasterboard sheeting following quickly behind. Glazing installation also continues progress up the building and is currently at level 12.

CLICK TO LEARN MORE ABOUT THE PATTERSON

Grace by Mosaic | Burleigh Heads

Address: 4-6 Second Avenue, Burleigh Heads

Apartments: 47

Builder: Mosaic Construction

Sales Status: Sold out

September is an extremely exciting month as we will officially reach building top out! The level 16 concrete slab is poured, and formwork has been stripped up to level 15. Windows are installed to level 14, walls are framed to level 13, services rough-in is finalised to level 12, and sheeting is complete to level 11. Joinery is underway to level 8, and tiling has commenced to level 10. Painting is also progressing internally, currently at level 10. All of these works will continue up the tower over the coming months.

CLICK TO LEARN MORE ABOUT GRACE

Dawn by Mosaic | Mermaid Beach

Address: Peerless Ave, Mermaid Beach

Apartments: 86

Builder: Hutchinson Builders

Sales Status: Sold out

Hutchinson Builders continue advancing the concrete slab pours, now at level 5. In other good news, the lift and stairs system as the core of the building is at level 11, and the tower perimeter containment screens are being installed. Scaffold stripping is underway to the basement and podium, and the external site sheds at the front of the site are in the process of being removed.

CLICK TO LEARN MORE ABOUT DAWN

The Witton by Mosaic | Indooroopilly

Address: 29 Finney Road, Indooroopilly

Apartments: 141 over two boutique buildings

Builder: Mosaic Construction

Sales Status: Sold out

There was certainly no slowing down over August at The Witton. With the construction of the capping beam finalised, the team has officially commenced basement excavation to Witton One at the rear of the site. Works are also underway on Witton Twos lift and stair core, which will be poured this month.

CLICK TO LEARN MORE ABOUT THE WITTON

Augusta | Burleigh Heads

Address: 4 First Ave, Burleigh Heads

Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels

Builder: Mosaic Construction

Sales Status: Sold out

Mosaic Construction continues to make solid progress towards the official commencement of basement excavation. All going to plan, and weather permitting, these works will commence this month. The dewatering system has been installed to remove groundwater or surface water during excavation. September will also see the completion of the pad mount transformer and underground conduits for the building’s power distribution.

CLICK TO LEARN MORE ABOUT AUGUSTA 

Florence | Burleigh Heads

Address: 42 The Esplanade, Burleigh Heads

Apartments: 9 full-floor Masterpiece Series residences over 9 levels

Builder: Mosaic Construction

Sales Status: Sold Out

Given they are adjoining sites, Florence by Mosaic and Augusta by Mosaic are being built at the same time. Per the above, Mosaic Construction is progressing towards the official commencement of basement excavation and installing the dewatering system.

CLICK TO LEARN MORE ABOUT FLORENCE

Bianca by Mosaic | Bilinga

Address: 1 Surf Street, Bilinga

Apartments: 13, 3-bedroom Masterpiece Series residences over seven levels

Builder: Mosaic Construction

Sales Status: Sold Out

The upgrade project to extensively improve a 16m portion of the existing sea wall on Bianca’s beachfront is complete. Mosaic Construction’s focus has shifted to preparing for Bianca’s initial site excavation activities. The first step will be piling, which will kick off mid this month, all going to plan and weather permitting.