Close

Construction Progress Round-up – November 2026

October was defined by a series of significant construction milestones across the Mosaic portfolio. From Palm Beach, where Sophia achieved structural top-out, to Kangaroo Point, where The Bedford has begun revealing its distinctive façade, several projects have entered pivotal new stages of delivery. Together, these milestones reflect another strong month of construction activity as projects continue to take shape across South East Queensland.

Brisbane

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 141, 2- and 3-bedroom apartments and penthouse-style Sky Homes over 17 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

The Bedford has reached an exciting new stage, with façade installations now emerging across the lower levels and Mosaic Construction beginning a genuinely transformative stage in the project. Despite challenging weather conditions in October, construction advanced steadily from Level 6 to Level 8, while internal works commenced within the first residences. Looking ahead, the structure is forecast to reach Level 10 during November, taking the project beyond the halfway point of its 18-level construction program as façade and fit-out works continue across the lower levels.

 

 

 

The Carter by Mosaic | Kangaroo Point

Address: 73-83 Linton Street, Kangaroo Point

Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

October represented a major milestone for The Carter, with the façade now complete and the building fully enclosed. Rooftop wellness amenities continued to take shape, including completion of the sauna fit-out and progress to the spa and cold plunge. Across the residences, fit-out works advanced rapidly through the upper levels, with waterproofing, tiling, joinery, flooring and services continuing in sequence. With lifts now operational and quality assurance inspections underway, the project continues to track strongly towards its mid-2027 completion.

 

CLICK TO LEARN MORE ABOUT THE CARTER

The Riversdale by Mosaic | South Brisbane

Address: 91 Montague Road, South Brisbane

Apartments: 213, 2- & 3-bedroom residences & sky homes over 39 levels

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: Over 65% Sold

The Riversdale continues to build strong momentum, with key early-stage construction milestones achieved throughout October, including completion of retention piling, site establishment and permanent perimeter hoarding. Foundation works are now approaching completion, paving the way for the installation of the tower crane and the start of vertical construction. As activity intensifies across the site, further perimeter and core structure works will continue, positioning the project for its next significant phase of delivery.

 

CLICK TO LEARN MORE ABOUT THE RIVERSDALE

Gold Coast

Madeline by Mosaic | Broadbeach

Address: 22 Mary Avenue, Broadbeach

Apartments: 60, half- and full-floor residences and Sky Homes over 39 levels

Builder: Mosaic Construction

Design Partner: Fraser and Partners

Sales Status: Over 80% Sold

Construction at Madeline continued to advance, rising through Levels 8 and 9, with preparations for Level 10 commencing ahead of schedule, while the central core progressed through Levels 12 and 13. Façade works and architectural finishes also advanced, alongside waterproofing and glazing to the lower levels. Significantly, the first residential fit-out activities commenced, marking the transition from structure to homes taking shape. Looking ahead, the tower is forecast to reach Level 12, with internal framing and services expanding across additional residences.

 

CLICK TO LEARN MORE ABOUT MADELINE

 

 

Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach

Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status:  Limited Opportunities Remain – Act Quickly

October marked a major milestone for Sophia, with Mosaic Construction achieving structural top-out following completion of the final rooftop concrete pour. With the primary structure now complete, rooftop works and façade glazing continued to advance, while internal fit-out activities gained momentum across the residences. Framing, services, sheeting, waterproofing and painting progressed throughout multiple levels, signalling the transition into the next stage of delivery. Looking ahead, glazing and internal finishes will continue to advance as Sophia moves closer to a mid-2027 completion.

 

CLICK TO LEARN MORE ABOUT SOPHIA

Josephine by Mosaic | Burleigh Heads

Address: 166 The Esplanade, Burleigh Heads

Apartments: 30 half- and full-floor residences across 18 levels.

Builder: Mosaic Construction

Design Partner: EMK Architects

Sales Status: Over 85% Sold – Act Now

Josephine continues to gather momentum as construction advances from site establishment into the foundation phase. Throughout October, key enabling works were completed, including installation of site infrastructure, dewatering systems and foundation preparation activities. Looking ahead, excavation is set to commence as part of the project’s top-down construction methodology, while capping beam and pile works continue. Together, these milestones will establish the structural platform required for the next stage of construction.

 

CLICK TO LEARN MORE ABOUT JOSEPHINE