7 May 2026
April’s inclement weather did little to slow progress on site as Mosaic Construction maintained strong momentum across Brisbane and the Gold Coast. From significant milestones made on the tower structures at The Bedford and The Carter, both in Brisbane’s Kangaroo Point, to the progression of Isabel’s unveiling to Burleigh Heads. Meanwhile construction continues for Madeline in Broadbeach and Sophia in Palm Beach with early site works on track at Josephine.
Brisbane
The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point
Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 17 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Over 90% Sold – Act Now
The Bedford has reached a major milestone, completing the Formwork–Reinforcement–Pour cycle across all basement levels as the structure begins rising above ground. April works included suspended slab pours, precast panel installation, and commissioning a second tower crane to boost efficiency. Scaffolding also commenced at podium level. In May, works will focus on further slab pours, precast installation, Level 1 framing, and essential services connections in Basement Level 4.
CLICK TO LEARN MORE ABOUT THE BEDFORD


The Carter by Mosaic | Kangaroo Point
![]()
Address: 73-83 Linton Street, Kangaroo Point
Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Over 90% Sold – Act Now
The Carter’s tower continues to rise, with the core reaching Level 17 and slab pours completed on Levels 12 to 14. Façade glazing progressed to Level 10, while scaffolding removal of the lower floors has revealed the building’s emerging design. Internally, party walls reached Level 9 and unit framing began on Level 7. In May, works will focus on higher slab pours, glazing advancement, internal finishes, and completing a benchmark apartment to set quality standards.


Gold Coast
Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads
Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.
Builder: Mosaic Construction
Design Partner: Koichi Takada Architects
Sales Status: SOLD OUT
CLICK TO LEARN MORE ABOUT ISABEL


Madeline by Mosaic | Broadbeach

Address: 22 Mary Avenue, Broadbeach
Apartments: 59, half- and full-floor residences and Sky Homes over 37 levels
Builder: Mosaic Construction
Design Partner: Fraser and Partners
Sales Status: Over 80% Sold
Madeline’s basement works continue to progress with Mosaic Construction maintaining strong progress across the basement FRP cycle, completing the Level 2 slab pour, wall shotcreting and precast column installation. Core walls advanced to Ground Floor, with formwork commencing at Basement Level 1. In May, works will continue toward the above-ground transition, including the Level 1 slab pour, further shotcreting, precast installation, continued core wall progression to Levels 2 and 3, and Ground Floor formwork.
CLICK TO LEARN MORE ABOUT MADELINE


Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach
Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: Limited Opportunities Remain – Act Quickly
Mosaic Construction maintained strong momentum across Sophia’s basement and ground level works, with the jump core reaching ground level—marking the shift to vertical construction. Ramp works progressed, while shotcrete neared completion, enabling removal of temporary supports. FRP activities advanced across Basement 1, including columns and core works. In May, focus will turn to ground floor pours, precast installation and scaffolding, while basement works continue, supporting services coordination and ongoing structural progression.


Josephine by Mosaic | Burleigh Heads

Address: 166 The Esplanade, Burleigh Heads
Apartments: 30 half- and full-floor residences across 18 levels.
Builder: Mosaic Construction
Design Partner: EMK Architects
Sales Status: Over 85% Sold – Act Now
April’s inclement weather had minimal impact at Josephine, with Mosaic Construction maintaining strong momentum across early site works. A fully engineered top-down demolition of the six-storey building is underway, enabling controlled, precise removal. Demolition will continue through May, before transitioning to the main construction program, including civil service connections, piling and excavation as the project moves into its next phase.
CLICK TO LEARN MORE ABOUT JOSEPHINE