Mosaic Construction closed the first quarter of 2026 achieving significant milestones across Brisbane and the Gold Coast — from the gradual unveiling of Isabel and early momentum at Josephine, both in Burleigh Heads, to rising forms in Kangaroo Point at The Carter and The Bedford.

Brisbane

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 17 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

The Bedford continues to progress through the Formwork–Reinforcement–Pour (FRP) cycle, with the building steadily transitioning out of the basement phase. During March, precast concrete panels were installed from Basement Level 1 toward Ground Floor, alongside suspended slab pours across Basement Level 2 Mezzanine, Basement Level 1 and Ground Floor decks and ramps. A key milestone was the arrival and staged installation of the second tower crane. In April, basement works will be finalised, with the building beginning to emerge above ground. Structural works will continue to Ground Floor and Level 1, external scaffolding will commence at podium level, and the new crane will enhance site efficiency once commissioned.

CLICK TO LEARN MORE ABOUT THE BEDFORD

 

The Carter by Mosaic | Kangaroo Point

Address: 73-83 Linton Street, Kangaroo Point

Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

The Carter continues to progress confidently through its upper structural stages, now well above ground. In March, the building advanced beyond its midpoint, with the core constructed to Level 15 and concrete pours completed on Levels 10 and 11. Façade works progressed concurrently, with glazing installed to Levels 7 and 8, enhancing the building’s architectural definition. Internal works also moved upward, with party wall framing commencing at Level 7. A key services milestone was achieved with completion of the Energex padmount site. In the coming month, the core is scheduled to reach Level 17, with slab pours to Levels 12–14, further façade installation, and continued progression of internal framing.

CLICK TO LEARN MORE ABOUT THE CARTER

 

Gold Coast

Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: SOLD OUT

March marked a major milestone for Isabel with the commencement of scaffold removal, revealing the building’s architectural form. Sections from Levels 19 to 17 have now been dismantled, generating strong early feedback that reflects the success of the original design vision. During the month, roof‑level services and screening were completed, while internal works continued to progress. In April, scaffold removal is set to continue down to Level 14, alongside further waterproofing on Levels 15 and 16 and ongoing fit‑out works.

CLICK TO LEARN MORE ABOUT ISABEL

 

Madeline by Mosaic | Broadbeach

Address: 22 Mary Avenue, Broadbeach

Apartments: 59, half- and full-floor residences and Sky Homes over 37 levels

Builder: Mosaic Construction

Design Partner: Fraser and Partners

Sales Status: Over 80% Sold

Madeline’s basement works continue to progress through a well‑sequenced below‑ground program, laying the groundwork for the structure above. In March, the Basement 3 raft pour was completed, marking a critical structural milestone. At the same time, the Formwork–Reinforcement–Pour (FRP) cycle advanced through the core walls from Basement 3 to Basement 2. A key milestone was the installation of the self‑climbing jump form system, supporting future vertical construction. In the coming period, works will focus on pouring the Basement 2 suspended slab, continued shotcreting, precast column installation, and progressing core walls up to Basement 1.

CLICK TO LEARN MORE ABOUT MADELINE

 

Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach

Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status:  Limited Opportunities Remain – Act Quickly

Sophia is now well established within the Formwork–Reinforcement–Pour (FRP) cycle, guiding the delivery of core concrete elements. Key basement milestones achieved include completion of the Basement 2 raft slab, Basement 2 lift core, fire stairs, and the ramp linking Basement 2 and Basement 1. Shotcrete works to Basement 2 are nearing completion, alongside successful pours to Basement 1. Throughout April, FRP activities will continue within Basement 1, retention struts will be progressively removed, and early works will commence to support the transition to the first ground floor pours.

CLICK TO LEARN MORE ABOUT SOPHIA

Josephine by Mosaic | Burleigh Heads

Address: 166 The Esplanade, Burleigh Heads

Apartments: 30 half- and full-floor residences across 18 levels.

Builder: Mosaic Construction

Design Partner: EMK Architects

Sales Status: Over 85% Sold – Act Now

Josephine continues to track strongly toward a complete sell‑out, with Mosaic Construction making steady progress on early site works. During March, all existing services and infrastructure across the site were permanently disconnected, removed, and decommissioned, including utilities servicing the former building. With these works successfully completed and the site secured, Mosaic has transitioned into full demolition of the existing structure. Demolition activities are now underway and scheduled to continue throughout April, clearing the site in readiness for the next phase of construction.

CLICK TO LEARN MORE ABOUT JOSEPHINE