Mosaic Construction continues to deliver on our promises, with Residents now settling into Marella by Mosaic following its February completion while The Manning by Mosaic has reached structural top-out. March is shaping up to be another milestone month, with The Prescott by Mosaic on track for settlement in the coming weeks. Meanwhile, our other projects continue to rise at pace.
Address: 17 The Esplanade, Cotton Tree
Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: SOLD OUT
At Building 1 (The Esplanade), Mosaic Construction has now completed the external façade screen installation down to Level 3, with the remaining lower-level screens on track for completion this month, weather permitting. Additionally, the team is in the final stage of scaffold removal, which is set for imminent completion.
Significant progress is likewise being made at Building 2 (Memorial Avenue), with internal works advancing, mechanical, electrical and plumbing services installed and scaffold removal continuing throughout March.
CLICK TO LEARN MORE ABOUT COTTON TREE
Address: 33 Railway Tce, Milton
Apartments: 113, 2- and 3-bedroom apartments over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: SOLD OUT
In February, Mosaic Construction reached the structural top-out, marking the completion of the building’s core structure and paving the way for a rooftop recreational space.
Inside, progress continues steadily. High-level services and window installation are finished up to Level 19. Party wall framing is complete to Level 16, and internal sheeting is in progress. On the lower levels, joinery installation is nearly complete on Level 9, and flooring installation has begun.
CLICK TO LEARN MORE ABOUT THE MANNING
Address: 28 Lissner Street, Toowong
Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels
Builder: Mosaic Construction
Design Partner: DKO
Sales Status: SOLD OUT
Mosaic Construction remains focused on the final key stages, including removing the scaffold and crane, completing ground-floor landscaping, finalising recreational amenities and common areas, and adding the last internal and external finishing touches.
The Prescott has also achieved an ‘as-built’ 6-Leaf EnviroDevelopment certification—a testament to Mosaic’s unwavering commitment to delivering not only high-quality homes but also sustainable, future-focused residences.
CLICK TO LEARN MORE ABOUT THE PRESCOTT
Address: 16-30 Prospect Street, Kangaroo Point
Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 16 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Now Selling – Act Now
Mosaic Construction is preparing everything behind the scenes to start bringing The Bedford to life.
While piling works were initially expected to commence between late February and early March, the Council approvals process has taken slightly longer than anticipated; however, Mosaic Construction is working closely with the relevant authorities to finalise the remaining approvals, which are advancing well.
CLICK TO LEARN MORE ABOUT THE BEDFORD
Address: 96 The Esplanade, Burleigh Heads
Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.
Builder: Mosaic Construction
Design Partner: Koichi Takada Architects
Sales Status: NEAR SELLOUT – ACT NOW
In February, Mosaic Construction installed precast wall panels, and finalised the ground floor blockwork walls.
Formwork for the Level 2 deck is now underway, which will continue throughout March as Mosaic Construction prepares for the Level 2 concrete slab pour.
CLICK TO LEARN MORE ABOUT ISABEL
Address: 4 Rosewood Avenue, Broadbeach
Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels
Builder: Mosaic Construction
Design Partner: Plus Architecture
Sales Status: SOLD OUT
February saw Lily’s structure rise to Level 25, with the jump form now reaching Level 28.
In March, Mosaic Construction is targeting to achieve lock-up for residences up to Level 6, elevate the jump form to Level 31 (the building’s full height), and pour the Level 28 concrete slab, weather permitting.
CLICK TO LEARN MORE ABOUT LILY