The Carter by Mosaic
73-83 Linton Street | Kangaroo Point
ViewAs we reach the midpoint of the year, momentum remains strong across Mosaic’s active construction sites, with each project progressing with confidence, energy, and precision. Excavation works are now being prepared at The Bedford by Mosaic and The Carter by Mosaic—key milestones that mark the next stage of delivery. Meanwhile, final detailing continues at Cotton Tree by Mosaic and The Manning by Mosaic, with both developments on track for completion in the coming months.
Address: 17 The Esplanade, Cotton Tree
Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: SOLD OUT
We’re in the final countdown at Cotton Tree, with move-in day fast approaching. The tower crane is down, and both buildings are deep into final detailing and defecting. Landscaping, blinds, and key amenity works are now underway. Despite some weather delays, momentum remains strong as we head toward completion.
CLICK TO LEARN MORE ABOUT COTTON TREE
Address: 33 Railway Tce, Milton
Apartments: 113, 2- and 3-bedroom apartments over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: SOLD OUT
Construction at The Manning has entered its final stage, with focus shifting to detailed finishes and presentation. May saw major progress across the podium, façade, and interiors, while scaffold and hoist removal revealed the building’s full architectural form. Internal fit-outs and quality inspections are well underway, and resident amenities like the sauna and gym are taking shape. June will bring final touches to the exterior, carpark, and street frontage as we approach completion.
CLICK TO LEARN MORE ABOUT THE MANNING
Address: 16-30 Prospect Street, Kangaroo Point
Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 16 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Now Selling – Act Now
June marks a major milestone at The Bedford, with piling works now complete and momentum building fast. Capping beams and retention braces are progressing well as the site prepares for bulk excavation. The first of two tower cranes will arrive soon, signalling a dramatic ramp-up in activity. Essential services works will also commence along Ferry and Prospect Streets.
CLICK TO LEARN MORE ABOUT THE BEDFORD
Address: 73-83 Linton Street, Kangaroo Point
Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Now Selling – Act Now
Construction has officially commenced at The Carter, with piling now underway—marking the start of major structural works. This critical phase lays the foundation for everything to come. With site establishment complete, momentum is building fast. Exciting progress is now taking shape on site.
CLICK TO LEARN MORE ABOUT THE CARTER
Address: 96 The Esplanade, Burleigh Heads
Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.
Builder: Mosaic Construction
Design Partner: Koichi Takada Architects
Sales Status: NEAR SELLOUT – ACT NOW
Momentum at Isabel is strong as we move into June, with construction progressing steadily across all levels. May saw the successful pour of the Level 3 slab and core walls to Level 4, along with scaffold installation. Formwork for the Level 4 slab is now halfway complete. This month, work continues upward with the Level 4 and 5 slabs and further scaffold advancements.
CLICK TO LEARN MORE ABOUT ISABEL
Address: 4 Rosewood Avenue, Broadbeach
Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels
Builder: Mosaic Construction
Design Partner: Plus Architecture
Sales Status: SOLD OUT
Lily continues to rise at pace, with May marking major progress. Structural works hit Level 32, and the jumpform reached its final stop at Level 33. Windows climbed to Level 28, internal works advanced steadily, and residences up to Level 8 are now locked up and undergoing quality checks.
June will see Lily reach full height with structural top-out — a huge milestone as we head into the final chapters of construction.
CLICK TO LEARN MORE ABOUT LILY
Address: 1357 Gold Coast Highway, Palm Beach
Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: Now Selling – Register for Exclusive Access
Exciting progress continues at Sophia, with demolition works now nearly complete. The site is being cleared in preparation for piling—the next major milestone in construction. This foundational phase will begin shortly and take several weeks to complete. Early works, including site setup and Energex upgrades, are already finalised and keeping the project on track.
CLICK TO LEARN MORE ABOUT SOPHIA