Activity remains strong across Mosaic Construction’s portfolio, with key milestones achieved and significant progress made from early foundation works through to final delivery stages. Highlights include The Riversdale in South Brisbane advancing towards the commencement of its formal construction program, while Isabel in Burleigh Heads moves closer to completion. Together, these projects reflect the continued momentum across South East Queensland.
Brisbane
The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point
Apartments: 141, 2- and 3-bedroom apartments and penthouse-style Sky Homes over 17 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Over 90% Sold – Act Now
July saw strong progress at The Bedford, with multiple concrete pours completed across Levels 1 and 2, allowing construction to move into the residential levels. Works advanced on Level 3, including formwork, reinforcement and the first concrete pour, while services integration continued. A key milestone was the installation of external climbing screens, enhancing site safety as the building rises. A second construction hoist was commissioned, with Level 3 completion and early Level 4 works planned for August.

The Carter by Mosaic | Kangaroo Point
![]()
Address: 73-83 Linton Street, Kangaroo Point
Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: Over 90% Sold – Act Now
July delivered significant progress at The Carter, with the Level 22 concrete slab completed ahead of schedule, bringing structural top-out within reach. Façade glazing advanced to Level 16, while internal and fit-out works progressed across multiple levels. Residences on Levels 3, 4, 5 and 7 reached completion and entered quality assurance. Upcoming milestones include rooftop terrace and roof pours, permanent power activation, utility connections, further façade works, and completion of Levels 6 and 8 residences.

The Riversdale by Mosaic | South Brisbane

Address: 91 Montague Road, South Brisbane
Apartments: 213, 2- & 3-bedroom residences & sky homes over 39 levels
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: Over 60% Sold
Riversdale continues to progress steadily, with demolition, site clearance, approvals and site establishment now complete. Mosaic Construction has commenced foundation preparations, including site levelling ahead of engineered working platforms and specialist equipment mobilisation. Underground powerline works are also scheduled along Bouquet Street. Weather permitting, piling is expected to begin in early September, marking the first major structural milestone and a significant step forward in delivering the development.
Gold Coast
Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads
Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.
Builder: Mosaic Construction
Design Partner: Koichi Takada Architects
Sales Status: SOLD OUT
Isabel is evolving almost daily as layers of craftsmanship, bespoke detailing, and premium finishes come together in this final stage of delivery. Within the residences, carpet and stone benchtop installation have advanced through Level 17, painting is complete on Level 18, balcony tiling is underway on Level 16, and electrical fit-off continues throughout the building. Landscaping is taking shape with mature Dragon Trees enhancing the Level 2 gardens, while basement finishing works are now largely complete. Focus is shifting to Ground Lobby finishes and Isabel’s welcoming arrival experience.

Madeline by Mosaic | Broadbeach

Address: 22 Mary Avenue, Broadbeach
Apartments: 60, half- and full-floor residences and Sky Homes over 39 levels
Builder: Mosaic Construction
Design Partner: Fraser and Partners
Sales Status: Over 80% Sold
Madeline continued its strong momentum throughout July, with completion of the Level 3 floor slab and planter structures, extension of the core to Level 6, and progress on Level 4 slab preparations. Precast panels and a new construction hoist were installed, improving site efficiency. Basement milestones included decommissioning dewatering systems and installing key infrastructure. In August, works will focus on Levels 4 and 5 slabs, advancing the core, commencing basement services, and removing elevated site sheds.


Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach
Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: Limited Opportunities Remain – Act Quickly
Sophia continued to rise above the Palm Beach foreshore in July, with Levels 3 and 4 slabs and core walls completed. A new project hoist improved site access and efficiency, while permanent internal walls began forming at ground level. Glazing preparations and waterproofing works also progressed. Looking ahead, Mosaic Construction is targeting completion of Levels 5 and 6, alongside continued glazing, services installation, internal fit-out preparations, and commencement of key electrical infrastructure works.

Josephine by Mosaic | Burleigh Heads

Address: 166 The Esplanade, Burleigh Heads
Apartments: 30 half- and full-floor residences across 18 levels.
Builder: Mosaic Construction
Design Partner: EMK Architects
Sales Status: Over 85% Sold – Act Now
July marked a key milestone at Josephine, with piling works commencing as planned along the southern and western site boundaries, establishing foundations for upcoming bulk earthworks. Piling will continue throughout August, weather permitting. The project will also see installation of essential site infrastructure, including the gantry, hoarding and elevated site facilities, supporting safe pedestrian access, efficient operations and the continued growth of construction activity.