Construction Progress Round-up – October 2023

Mosaic Property
03/10/23

With a number of Mosaic cranes now sitting proudly on the South East Queensland skyline, we are pleased to offer our valued customers and stakeholders the latest update on the significant ongoing progress made by our award-winning construction team across our 13 active building sites

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Sales Status: NEAR SELLOUT – ENQUIRE NOW

With piling works complete and basement excavation officially underway at Lily, the momentum continues with capping beam installation also set to finish in the coming days.

Bulk excavation will continue through October, and the team will initiate shotcrete application to the basement walls as they progress deeper into the ground. This specialised technique involves spraying concrete at high velocity to reinforce and ensure durability during the dig.

The dewatering system installed in September will ensure the construction site remains dry and safe.

CLICK TO LEARN MORE ABOUT LILY

 

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Sales Status: SOLD OUT

Piling works were successfully completed in September, as was the stormwater connection. With the piling phase behind us, the team has commenced the installation of the capping beams. These horizontal structural elements will sit atop the piles, distributing the building’s weight evenly and strengthening the foundation.

Mosaic Construction also began essential inground hydraulic and electrical works for Building 1.  And should all go to plan and weather permitting, the team is targeting to install Cotton Tree’s tower crane at the end of October and install deep wells for dewatering purposes.

CLICK TO LEARN MORE ABOUT COTTON TREE

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT – ACT NOW

September saw the team achieve a significant milestone: The Manning’s tower crane installation. This month, the team is focused on achieving several goals, weather permitting, including pouring the Ground floor slab and forming the Ground to Level 1 vertical precast columns.

They are also set to finalise stormwater connections to the site. This is the infrastructure and systems to manage rainwater runoff from streets, buildings, and other surfaces during rainfall or storms. It is critical to prevent flooding, erosion, and water pollution.

CLICK TO LEARN MORE ABOUT THE MANNING

The Prescott by Mosaic | Toowong

Address: 28 Lissner Street, Toowong

Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT – ACT NOW

With The Prescott’s tower crane installed, the team has also made significant headway with bulk excavation and shotcrete application to the basement walls, with this critical phase now all but complete.

Energex’s undergrounding of the overhead powerlines to the front of The Prescott’s site was also successfully finalised in September as planned.

In preparation for the next construction phase, the team has commenced detailed excavation and also begun work on in-ground services.

Should all go to plan and weather permitting, Mosaic Construction will kickstart the process of pouring the Basement 2 concrete slab, another significant and exciting milestone.

CLICK TO LEARN MORE ABOUT THE PRESCOTT

Lorient by Mosaic | Maroochydore

Address: 88 Duporth Ave, Maroochydore

Apartments: An ultra-luxury collection of 15 half and full-floor penthouse-style residences.

Builder: Mosaic Construction

Sales Status: SOLD OUT

October will see another month of excellent advancement on-site by Mosaic Construction with advancements to the building’s internal elements.

Externally, the team is making solid headway with the soffit cladding and external render, while in the recreation building, the Level 2 slab has been poured, setting the stage for this vibrant communal space.

In addition to advancing the above works, Mosaic Construction is set to reach a significant milestone as they will shortly start to drop Lorient’s scaffolding, progressively revealing its stunning façade.

CLICK TO LEARN MORE ABOUT LORIENT

Luca by Mosaic | Kirra

Address: 7 Douglas Street, Kirra

Apartments: 31

Builder: Mosaic Construction

Sales Status: SOLD OUT

After last month’s massive milestone of structural top-out, the team is now set to gradually remove Luca’s scaffold. External painting and render work are in full swing, as is the construction of Luca’s swimming pool.

As we move into October, the installation of mechanical and electrical services should be complete by the end of the month. At the same time, internal spaces will start to take shape with painting, joinery fit-out, stone bench top installation, and carpet laying.

Externally, the team is targeting to commence fitting the facade trellis shortly. Planter filling will also get underway, bringing greenery and a natural touch to the surroundings.

CLICK TO LEARN MORE ABOUT LUCA

Dawn by Mosaic | Mermaid Beach

Address: Peerless Ave, Mermaid Beach

Apartments: 86

Builder: Hutchinson Builders

Sales Status: SOLD OUT

One of the most significant events of September was the removal of the crane from the site. In further good news, Dawn’s second lift is fully operational, while solar panel installation has been completed. The vibrant common areas at Ground, Level 2 and Level 9 are also progressing well through their final stages.

In addition to finishing works, Hutchies will commission and test various building services during October, ensuring that everything operates seamlessly.

CLICK TO LEARN MORE ABOUT DAWN

The Witton by Mosaic | Indooroopilly

Address: 29 Finney Road, Indooroopilly

Apartments: 141 over two boutique buildings

Builder: Mosaic Construction

Sales Status: SOLD OUT

The team successfully poured Witton One’s Level 9 concrete slab in September, meaning we are now over the structural halfway mark for this tower.

Construction activities continue to accelerate, with further concrete pours to both Witton One and Two set to take place this month, weather permitting.

Preparations for the electrical transformer, carried out by Energex, have been completed. The team is also diligently working on finalising the critical water and sewer site connections.

CLICK TO LEARN MORE ABOUT THE WITTON

Augusta by Mosaic | Burleigh Heads

Address: 4 First Ave, Burleigh Heads

Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

Mosaic Construction successfully poured both the Level 7 and Level 8 concrete slabs and forming the vertical elements necessary to progress.

The installation of essential services, such as plumbing and electrical systems, continues progressing to the lower levels, as is internal wall framing and window installation.

The team also kicked off external waterproofing last month. Weather permitting, October sees the team prepping for the Level 11 slab pour.

CLICK TO LEARN MORE ABOUT AUGUSTA 

Florence by Mosaic | Burleigh Heads

Address: 42 The Esplanade, Burleigh Heads

Apartments: 9 full-floor Masterpiece Series residences over 9 levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

September was another month of excellent advancement on-site by Mosaic Construction, with the team successfully pouring the Level 5 concrete slab.

The installation of essential services, such as plumbing and electrical systems, has commenced and is currently underway at the lower levels.

Weather permitting, October sees the team targeting to complete both the Level 6 and Level 7 concrete slab pours and start prepping for the Level 8 pour. Services rough-in will also persist through the month while window installation will begin.

CLICK TO LEARN MORE ABOUT FLORENCE

Bianca by Mosaic | Bilinga

Address: 1 Surf Street, Bilinga

Apartments: 13, 3-bedroom Masterpiece Series residences over seven levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

The team continues to make significant advancements, with wall sheeting complete up to Level 6, painting complete up to Level 3, and joinery installed up to Level 2.

External tiling was finalised in September, and screen installation is ongoing. Mosaic Construction has also commenced dropping the scaffold, progressively revealing Bianca’s facade.

October will see the team targeting to complete wall sheeting and painting to all remaining levels and progress with joinery installation.

CLICK TO LEARN MORE ABOUT BIANCA

The Mowbray by Mosaic | East Brisbane

Address: 73 Northcote Street, East Brisbane

Apartments: 81, 2- and 3-bedroom residences over 8 levels

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT.

Excitingly, the ground-level concrete slab was successfully poured last month, with the team then pushing ahead with forming the vertical precast components for Level 1.

The positive momentum will continue with the commencement of services fit-out to the basement levels in October. Should all go to plan, and weather permitting, this month will also see the installation of the striking feature “V” columns at ground level while construction of the Level 2 podium slab will begin.

CLICK TO LEARN MORE ABOUT THE MOWBRAY

Marella by Mosaic | Broadbeach

Address: 146 Surf Parade, Broadbeach

Apartments: 100, 2- and 3-bedroom residences over thirty levels

Builder: Mosaic Construction

Sales Status: Sold Out

September saw the team successfully complete the Level 2 and Level 3 concrete slab pours. Dewatering equipment has now been removed from the site to allow for essential services such as electricity and water connections to get underway to the basement levels.

October focuses on advancing the concrete slab pours, weather permitting, and ongoing basement services installation.

And in another exciting milestone, October will see the commencement of Marella’s façade installation, starting to give shape to the building’s elegant and distinctive look and character.

CLICK TO LEARN MORE ABOUT MARELLA