Project updates | 3 minutes

Construction Progress Round-up – November 2023

Mosaic Property
06/11/23

As we near the end of 2023, our 13 construction sites are currently advancing through different stages of their building program. We're thrilled to showcase the remarkable progress made over the past month, as we extend a warm welcome to new Residents at Dawn by Mosaic and gear up for the anticipated completion of another project later this year.

Isabel by Mosaic | Broadbeach

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: SELLING FAST – ENQUIRE NOW

Early construction works are advancing to schedule, with demolition of the existing structure on-site due to be completed in the coming weeks and the formal building program to follow.

CLICK TO LEARN MORE ABOUT ISABEL

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: NEAR SELLOUT – ENQUIRE NOW

October saw Mosaic Construction complete the capping beam installation, a critical element of Lily’s structural foundation. Temporary power was also established to cater to the diverse range of construction activities and keep tasks on track, including the dewatering system, which is now operational and managing groundwater levels as the team progresses with bulk excavation.

As October unfolded and this massive task continued its descent into the ground, the team began applying shotcrete to the walls of Basement 1. Weather permitting, the team is looking to complete bulk excavation this month and install Lily’s tower crane.

CLICK TO LEARN MORE ABOUT LILY

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

October saw the team achieve a series of milestones, with capping beam works and essential in-ground hydraulic and electrical works to Building 1 officially complete.

This month, should all go to plan and weather permitting, the team is set to realise a momentous achievement in Cotton Tree’s construction journey: the tower crane installation. The final stages of preparation for excavation will be closed out, and the site’s sewer connection is set to get underway.

CLICK TO LEARN MORE ABOUT COTTON TREE

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: NEARING SELLOUT – ACT NOW

With The Manning’s foundations firmly established, the team worked diligently through October, successfully completing the ground-level concrete slab pour and installing vertical load-bearing columns that will evenly distribute the building’s weight across its foundations.

As we transition into November, the team will target an array of essential works, including forming the ground-level lift and stair core and installing a collision wall on the Queensland Rail boundary, a critical safety measure for the local community.

Mosaic Construction will also oversee the installation of the stormwater tank as well as the Energex pad mount transformer, which will eventually provide the building’s electrical supply.

CLICK TO LEARN MORE ABOUT THE MANNING

The Prescott by Mosaic | Toowong

Address: 28 Lissner Street, Toowong

Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels

Builder: Mosaic Construction

Design Partner: DKO

Sales Status: NEARING SELLOUT – ACT NOW

With The Prescott’s tower crane now standing proudly on the Toowong skyline, the team reached another momentous milestone in October, finalising bulk excavation. Detailed excavation for in-ground services, the lift pit, and stairs were also closed out last month, carving out space for essential systems encompassing the site’s water supply, drainage and electrical wiring.

This month, Mosaic Construction aims to complete The Prescott’s Basement 2 concrete slab pour, the very first concrete slab pour for the building. Following this, should all go to plan and weather permitting, the team will then look to form vertical elements to advance from Basement 2 to Basement 1.

CLICK TO LEARN MORE ABOUT THE PRESCOTT

Lorient by Mosaic | Maroochydore

Address: 88 Duporth Ave, Maroochydore

Apartments: An ultra-luxury collection of 15 half and full-floor penthouse-style residences.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

Last month’s biggest highlight, indeed one of the most significant of the entire construction journey, was the start of unveiling Lorient’s magnificent silhouette. Living spaces are also coming to life, with joinery installation and tiling progressing to level 5 and timber flooring to level 3.

November has Mosaic Construction targeting to complete timber floor laying up to Level 5, joinery installation up to Level 7, and stone benchtop fitting up to Level 6.

The team also aims to finish the swimming pool structure, advance external rendering works, continue with scaffold removal, and frame and sheet the recreation building’s interiors.

CLICK TO LEARN MORE ABOUT LORIENT

Luca by Mosaic | Kirra

Address: 7 Douglas Street, Kirra

Apartments: 31

Builder: Mosaic Construction

Design Partner: Gatehouse Architects

Sales Status: SOLD OUT

Last month, Luca’s facade was revealed! The interiors are also taking final shape, with kitchens installed up to Level 2. If all goes according to plan, kitchens will be installed on all remaining levels by the end of November.

This month will also see painting to the exterior facade closed out and pool works propelled towards completion.

CLICK TO LEARN MORE ABOUT LUCA

Dawn by Mosaic | Mermaid Beach

Address: Peerless Ave, Mermaid Beach

Apartments: 86

Builder: Hutchinson Builders

Design Partner: Plus Architecture

Sales Status: SOLD OUT

We are excited to share that, this month, we are officially welcoming Residents home to Dawn by Mosaic! Handing over this building is a momentous occasion that we have all eagerly anticipated, and we couldn’t be more honoured to share this milestone.

CLICK TO LEARN MORE ABOUT DAWN

The Witton by Mosaic | Indooroopilly

Address: 29 Finney Road, Indooroopilly

Apartments: 141 over two boutique buildings

Builder: Mosaic Construction

Design Partner: Rothelowman

Sales Status: SOLD OUT

October saw Mosaic Construction complete Witton One’s Level 11 concrete slab pour, progress internal works to Levels 4 and 5, and finalise the site’s water connection. Excitingly, Witton Two will be officially on the ascent this month, with the Level 1 concrete slab pour set to be closed out in the coming days.

Mosaic Construction also aims to complete Witton One’s Levels 12 and 13 concrete slab pours while simultaneously continuing internal works up the building this month.

A particular highlight, weather permitting, will be commencing the process of installing the distinguishing feature columns to Witton One’s exterior facade, a key element to the development’s overall design intent and aesthetic.

CLICK TO LEARN MORE ABOUT THE WITTON

Augusta by Mosaic | Burleigh Heads

Address: 4 First Ave, Burleigh Heads

Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: SOLD OUT

October saw the team complete the Levels 9 and 10 concrete slab pours and prepare for the Level 11 pour. We also saw solid headway with services rough-in, internal wall framing and window installation, external waterproofing and external rendering works.

Looking to the month ahead, should all go to plan and weather permitting, Mosaic Construction aims to complete Augusta’s Levels 11 and 12 concrete slab pours. Following this, they will form the vertical elements connecting Level 12 to Level 13, meaning we are well and truly on the home stretch to structural top-out!

November will see the commencement of internal tiling, joinery installation, and painting.

CLICK TO LEARN MORE ABOUT AUGUSTA 

Florence by Mosaic | Burleigh Heads

Address: 42 The Esplanade, Burleigh Heads

Apartments: 9 full-floor Masterpiece Series residences over 9 levels

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

October saw the team successfully complete Florence’s Levels 6 and 7 concrete slab pours, paving the way for preparations to commence for Level 8. Services rough-in continued, and excitingly, window installation commenced, giving us a first glimpse at Florence’s inspiring views.

As we look ahead to November, the team is targeting completion of the Levels 8 and 9 concrete slab pours, should all go to plan and weather permitting. They will then start forming the vertical elements connecting Level 9 to the roof, indicating they are close to achieving a momentous milestone: Florence’s structural top-out.

Window installation and services rough-in will continue through November, and wall partition framing will get underway.

CLICK TO LEARN MORE ABOUT FLORENCE

Bianca by Mosaic | Bilinga

Address: 1 Surf Street, Bilinga

Apartments: 13, 3-bedroom Masterpiece Series residences over seven levels

Builder: Mosaic Construction

Design Partner: SJB Architects

Sales Status: SOLD OUT

Last month’s biggest highlight, indeed one of the most significant of the entire construction journey, was the unveiling of Bianca’s magnificent silhouette. Last month, the team also completed the driveway, all exterior painting, and installation of all external screens from Level 2 up to Level 7.

Living space are really coming to life, with tiling and joinery forecast to be finalised across all levels this month, followed by appliance installation. The team will also focus on landscaping and finishing works in the communal areas.

CLICK TO LEARN MORE ABOUT BIANCA

The Mowbray by Mosaic | East Brisbane

Address: 73 Northcote Street, East Brisbane

Apartments: 81, 2- and 3-bedroom residences over 8 levels

Builder: Mosaic Construction

Design Partner: DKO Architecture

Sales Status: NEARING SELLOUT

Excitingly, The Mowbray’s feature “V” precast columns, a key feature of its overall design intent that will distinguish the ground plane on Lytton Road, are now installed.

The team also successfully completed preparation for the Level 2 concrete slab pour, which is due to be completed early this month. Following this, the team will start forming Level 2’s vertical columns and prepping for the Level 3 concrete slab pour, weather permitting.

CLICK TO LEARN MORE ABOUT THE MOWBRAY

Marella by Mosaic | Broadbeach

Address: 146 Surf Parade, Broadbeach

Apartments: 100, 2- and 3-bedroom residences over thirty levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: Sold Out

The team’s well-executed program saw them complete Marella’s Level 5 concrete slab pour and progress the jump form up to Level 8 in October. The Energex pad mount transformer, which will ensure a reliable power supply for the entire building, was also installed last month.

Looking to this month, weather permitting, November’s targets include completing the Levels 6, 7, and 8 concrete slab pours and elevating the jump form to Level 11. Works on Marella’s facade are ongoing, including glazing installation and painting, revealed progressively as the jump form ascends.

CLICK TO LEARN MORE ABOUT MARELLA