Project updates | 3 minutes

Construction Progress Round-up – March 2024

Mosaic Property
01/03/24

As we welcome the arrival of autumn, we're pleased to share the latest progress update for our ten active construction sites across South East Queensland. The hard work and dedication of Mosaic Construction are evident in the numerous positive advancements made on various fronts.

Sunshine Coast

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

Basement works are ongoing while Building 1 (The Esplanade) has officially begun its above-ground ascent, with the Level 1 concrete pour successfully completed late last month as planned.

Mosaic Construction is now preparing for the Level 2 concrete slab, targeting its pour at the end of March, weather permitting.

CLICK TO LEARN MORE ABOUT COTTON TREE

Brisbane

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: NEARING SELLOUT – ACT NOW

Preparations for the Level 3 concrete slab were finalised last month as planned, with the team set to complete the pour shortly, weather permitting.  February also saw the team complete the concrete ramp connecting the podium car park levels.

In addition to the Level 3 concrete slab pour, Mosaic Construction’s key priorities for March extend to kicking off preparations for the Level 4 slab pour and installing plumbing and mechanical services at ground level.

The team will also look to connect and liven up the building’s main power boards.

CLICK TO LEARN MORE ABOUT THE MANNING

The Prescott by Mosaic | Toowong

Address: 28 Lissner Street, Toowong

Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels

Builder: Mosaic Construction

Design Partner: DKO

Sales Status: SOLD OUT

Last month, Mosaic Construction completed the first pour for The Prescott’s Level 1 slab, a massive task that required 770m3 of concrete due to the sheer size of the floor plate.

The second pour, which will comprise 550m3 of concrete this time, is set to take place any day now, weather permitting.

Following this, Mosaic Construction will get to work preparing for the Level 2 concrete slab pour, which will again take place in two parts due to scale.

Should all go to plan, and weather permitting, both these pours will take place before the end of March.

Below ground, essential fire and electrical high-level services are installed across Basements 1 and 2, ensuring a seamless integration of this crucial infrastructure within the building’s framework.

CLICK TO LEARN MORE ABOUT THE PRESCOTT

The Witton by Mosaic | Indooroopilly

Address: 29 Finney Road, Indooroopilly

Apartments: 141 over two boutique buildings

Builder: Mosaic Construction

Design Partner: Rothelowman

Sales Status: SOLD OUT

The Witton One is now standing at full height, with the team achieving structural top-out last month as planned.

On top of this, should all go to plan and weather permitting, the team is also on track to top out at Witton Two this month.

At Witton One, glazing installation has reached Level 13, services rough-in is at Level 7, and internal wall sheeting and setting are at Level 8.

In addition to topping out at Witton Two, March is a big month as the rooftop recreation space atop Witton One starts to form. Plans are underway to install landscaping planters, along with the building’s distinctive ‘crown,’ the elements of which are set to be lifted into position by crane.

CLICK TO LEARN MORE ABOUT THE WITTON

The Mowbray by Mosaic | East Brisbane

Address: 73 Northcote Street, East Brisbane

Apartments: 81, 2- and 3-bedroom residences over 8 levels

Builder: Mosaic Construction

Design Partner: DKO Architecture

Sales Status: SOLD OUT

Last month, the team completed the Level 6 concrete slab pour and kicked off preparation for the Level 7 slab, which, weather permitting, will take place this month in addition to the Level 8 slab pour.

Mosaic Construction has now started bringing The Mowbray’s internal spaces and homes to life, commencing with internal wall framing and glazing installation, which is now complete to Levels 1 and 2.

Looking ahead to March, in addition to the Levels 7 and 8 concrete slab pours, the team will keep progressing with services rough-in, window installation, and wall framing.

Wall sheeting and sanding will also start at the lowest levels in preparation for painting, which will follow in due course.

CLICK TO LEARN MORE ABOUT THE MOWBRAY

Gold Coast

Isabel by Mosaic | Broadbeach

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: NEAR SELLOUT  – ENQUIRE NOW

Mosaic Construction is shortly set to achieve another significant milestone as they finalise piling works around Isabel’s perimeter as planned.

Following this, they will turn their attention to trimming the piles to their specified height before initiating capping beam installation.

Capping beam works will persist throughout March as part of the critical pathway to Mosaic Construction kicking off bulk excavation.

CLICK TO LEARN MORE ABOUT ISABEL

Augusta by Mosaic | Burleigh Heads

Address: 4 First Ave, Burleigh Heads

Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: SOLD OUT

Following the recent achievement of structural top-out, Mosaic Construction has maintained its positive momentum, further shaping Augusta’s internal spaces while advancing the next phase of external finishing works.

Wall framing, sheeting, setting, and painting are progressing to level 10 and will keep moving through the last of the upper levels throughout the month.

Services rough-in has also reached Level 10, while joinery fit-out is closely behind, and reconstituted stone benchtop fitting is underway to kitchens, bathrooms, and laundries on Level 3.

Timber floor placement is pushing ahead on Level 4, and tiling to wet areas and balconies is progressing to Level 6.

Externally, works on Augusta’s undulating feature facade continue, alongside the final rendering and painting of all elevations.

In addition to the above, the lower levels will see the start of their final electrical and joinery fit-offs this month.

CLICK TO LEARN MORE ABOUT AUGUSTA 

Florence by Mosaic | Burleigh Heads

Address: 42 The Esplanade, Burleigh Heads

Apartments: 9 full-floor Masterpiece Series residences over 9 levels

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

Wall framing, sheeting, and setting are complete to level 5 and will keep advancing through the upper levels throughout the month.

Services rough-in is moving ahead on Level 6, while preparation for flooring installation, kicking off firstly with wet area tiling this month, is progressing to lower levels.

Additionally, March marks the commencement of internal wall painting at Level 2.

Externally, the installation of Florence’s feature facade screening continues alongside the concrete rendering of all elevations.

CLICK TO LEARN MORE ABOUT FLORENCE

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: NEAR SELLOUT – ENQUIRE NOW

Following the completion of the first basement slab pour, Mosaic Construction finished installing Lily’s jump form.

Below ground, basement works continue to progress as planned. Weather permitting, the team aims to hit several milestones in the coming weeks, culminating in completing Lily’s ground-floor slab pour.

CLICK TO LEARN MORE ABOUT LILY

Marella by Mosaic | Broadbeach

Address: 146 Surf Parade, Broadbeach

Apartments: 100, 2- and 3-bedroom residences over thirty levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: SOLD OUT

Marella’s magnificent tower form is now complete to Level 14, meaning we will shortly hit the structural halfway point.

Weather permitting, March will see the team progressively propel the jump form from Level 18 to Level 22, culminating in the Level 18 concrete slab pour.

Permanent power has been established to the site, supporting the team’s increased requirements as they continue Marella’s ascent while at the same time shaping its internal spaces.

Installation of the tinted glazing is advancing to Level 12, while internal wall and ceiling framing, sheeting, setting, and painting are closed out to Level 4.

Meantime, services rough-in is at Level 8, wet area tiling is advancing to Level 4, and joinery installation has kicked off at Level 3.

The team are also working on finalising Marella’s lift installation this month.

CLICK TO LEARN MORE ABOUT MARELLA

Register for Our Latest Releases