Construction Progress Round-up – June 2023

Mosaic Property
06/06/23

June is a monumental month for our 13 projects currently under construction, each at different build stages. Some are just starting to ascend from the ground, and others are just months away from building top out. It is an exciting time for our purchasers and team as we prepare to complete another 4 projects at the end of the year.

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT – ONE REMAINING

Excitingly, site establishment works are officially underway, with the team installing Cotton Tree’s sheds and hoarding on site shortly. Should all go to plan and weather permiting, piling works will commence this month for both buildings 1 and 2. Beforehand, the team will create working platforms to provide a reliable and stable surface on which a piling rig can operate safely.

CLICK TO LEARN MORE ABOUT COTTON TREE

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT – ACT NOW

It’s full steam ahead on-site, with Mosaic Construction continuing to make solid headway, having kicked off piling works to the site perimeter. As the team completes a section of piles, they will progressively form and pour the capping beams. Detailed excavation will commence upon the completion of piling works.

CLICK TO LEARN MORE ABOUT THE MANNING

The Prescott by Mosaic | Toowong

Address: 28 Lissner Street, Toowong

Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels

Builder: Mosaic Construction

Sales Status: NEARING SELLOUT – ACT NOW

May saw Mosaic Construction complete The Prescott’s perimeter piling works. With this critical task now complete, the team is advancing with capping beam works which will continue throughout June. Bulk excavation is set to kick off in the second half of June once the capping beam works are finalised. The team will begin digging into the top layer of dirt before progressing further into the basement levels throughout August.

CLICK TO LEARN MORE ABOUT THE PRESCOTT

Lorient by Mosaic | Maroochydore

Address: 88 Duporth Ave, Maroochydore

Apartments: An ultra-luxury collection of 15 half and full-floor penthouse-style residences.

Builder: Mosaic Construction

Sales Status: SOLD OUT

Lorient’s ascent is, excitingly, nearing its conclusion, with Mosaic Construction completing the level 6 slab pour in late May. June will see the team target the level 7 slab pour, weather pending, meaning we are getting very close to reaching building top out. Meanwhile, window installation is progressing to level 3 and plumbing and electrical services rough in to levels 2 and 3. Wall and ceiling framing is also underway to level 2 and sheeting to level 1.

CLICK TO LEARN MORE ABOUT LORIENT

Luca by Mosaic | Kirra

Address: 7 Douglas Street, Kirra

Apartments: 31

Builder: Mosaic Construction

Sales Status: SOLD OUT

Mosaic Construction has completed the level 1 slab pour and removed ground-level formwork. Lighting is also installed in the ground-level car park, as has access lighting to level 1. Meantime, the building’s sewer connections are finalised. This month, the team plans to complete the level 2 slab pour and commence prepping for the level 3 slab. Shotcreting will likewise get underway for the basement walls in June.

CLICK TO LEARN MORE ABOUT LUCA

Dawn by Mosaic | Mermaid Beach

Address: Peerless Ave, Mermaid Beach

Apartments: 86

Builder: Hutchinson Builders

Sales Status: SOLD OUT

Dawn’s core structure is now complete to its highest point. And with that, the jump form has been dismantled and removed, and Dawn’s stunning form is approaching its full reveal. Last month, Hutchinson Builders made excellent progress pouring the level 27 and 28 slabs, meaning there are only three more levels until Dawn’s top out.

CLICK TO LEARN MORE ABOUT DAWN

The Witton by Mosaic | Indooroopilly

Address: 29 Finney Road, Indooroopilly

Apartments: 141 over two boutique buildings

Builder: Mosaic Construction

Sales Status: SOLD OUT

Mosaic Construction is continuing to make solid headway on site, having completed the levels 2 and 3 slab pours for Witton One last month. Should all go to plan and weather permitting, the team is targeting to complete both Witton One’s levels 4 and 5 concrete slab pours this month.

CLICK TO LEARN MORE ABOUT THE WITTON

Augusta by Mosaic | Burleigh Heads

Address: 4 First Ave, Burleigh Heads

Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

Mosaic Construction keeps hitting major milestones on-site, having reached the level 2 slab pour. Weather permitting, the team is targeting to complete the level 3 slab pour and start formwork for the level 4 slab. Below ground, shotcreteing to the basement walls is scheduled to be finalised in June, while electrical and hydraulic services installation will keep advancing.

CLICK TO LEARN MORE ABOUT AUGUSTA 

Florence by Mosaic | Burleigh Heads

Address: 42 The Esplanade, Burleigh Heads

Apartments: 9 full-floor Masterpiece Series residences over 9 levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

With the ground-level slab pour complete, Mosaic Construction is progressing with structural wall works up to level 2, in preparation for the level 2 slab pour. The team is also targeting to install Florence’s pool shell this month. Given they are adjoining sites, Florence by Mosaic and Augusta by Mosaic are being built at the same time. As per above, below ground, shotcreteing to the basement walls is scheduled to be finalised in June, while electrical and hydraulic services fittings will keep advancing.

CLICK TO LEARN MORE ABOUT FLORENCE

Bianca by Mosaic | Bilinga

Address: 1 Surf Street, Bilinga

Apartments: 13, 3-bedroom Masterpiece Series residences over seven levels

Builder: Mosaic Construction

Sales Status: SOLD OUT

It’s a hive of activity on site at Bianca, with Mosaic Construction continuing to progress each residential level, having completed the levels 2 and 3 slab pours last month. Meanwhile, shotcreting is finalised to the basement walls, while services installation to this space is ongoing (i.e. water, electricity, plumbing). The June plan is to complete the levels 4 and 5 slab pours, weather permitting, and basement services installation.

CLICK TO LEARN MORE ABOUT BIANCA

The Mowbray by Mosaic | East Brisbane

Address: 73 Northcote Street, East Brisbane

Apartments: 81, 2- and 3-bedroom residences over 8 levels

Builder: Mosaic Construction

Sales Status: Only a couple remaining – move quickly.

Mosaic Construction continues making excellent progress, with bulk excavation continuing unimpeded, as seen in the images below. For added context, there are currently five excavators on site, with over 80 truckloads of dirt removed from the site daily. Excavation will continue through June, as will progressive shotcreting to the basement perimeter walls.

CLICK TO LEARN MORE ABOUT THE MOWBRAY

Marella by Mosaic | Broadbeach

Address: 146 Surf Parade, Broadbeach

Apartments: 100, 2- and 3-bedroom residences over thirty levels

Builder: Mosaic Construction

Sales Status: Sold Out

May was a monumental month on-site for Mosaic Construction, as they completed Marella’s first major concrete pour for the level 3 basement slab. For context, just over 1,850m3 of concrete was poured and pumped at approximately 240m3 an hour. The team ran 48 concrete agitators on turnaround and had three concrete plants exclusively servicing this task on the day. May also saw the building’s lift and core formwork and reinforcement works get underway, as well as basement 3 waterproofing and shotcreteing to the perimeter walls.  Precast elements from basement 3 to basement 2 are advancing, following which the team is targeting to pour the basement 2 slab this month, weather pending.

CLICK TO LEARN MORE ABOUT MARELLA