We are excited to kick off construction at Lily by Mosaic in Broadbeach, earlier than forecast, bringing our pipeline to 13 projects. This is an incredibly exciting time for our purchasers, and a testament to our team's commitment to delivering exceptional residences.
Address: 4 Rosewood Avenue, Broadbeach
Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels
Builder: Mosaic Construction
Sales Status: SELLING FAST – ENQUIRE NOW
The market interest in Lily by Mosiac has enabled us to bring construction commencement ahead of schedule, with our own award-winning construction arm already on site conducting early works. Demolition and site clearing will continue through July, after which the team will start formal preparations for basement excavation.
CLICK TO LEARN MORE ABOUT LILY
Address: 17 The Esplanade, Cotton Tree
Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.
Builder: Mosaic Construction
Sales Status: NEARING SELLOUT – ONE REMAINING
June saw Mosaic Construction finish installing their site sheds, which will remain in place for the duration of Cotton Tree’s build. All required construction documentation for the basement is also complete.This massive, critical task required meticulous planning and collaboration between our team and the appointed engineers. It forms the foundation for Cotton Tree’s entire building program. A piling rig has been mobilised and piling works will kick off to the perimeter of building 1 in the coming days.
CLICK TO LEARN MORE ABOUT COTTON TREE
Address: 33 Railway Tce, Milton
Apartments: 113, 2- and 3-bedroom apartments over 22 levels
Builder: Mosaic Construction
Sales Status: NEARING SELLOUT – ACT NOW
Mosaic Construction is set to complete piling works in the coming days. July is a massive month for the team, as they kick off detailed excavation for The Manning’s foundation. The focus will initially be on excavating the centre of the site in preparation for the commencement of the core foundations.
CLICK TO LEARN MORE ABOUT THE MANNING
Address: 28 Lissner Street, Toowong
Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels
Builder: Mosaic Construction
Sales Status: NEARING SELLOUT – ACT NOW
Mosaic Construction maintained a solid pace in June and is nearing completion of The Prescott’s piling works. Once complete, the team plans to commence basement excavation, a massive task expected to take six to eight weeks.
CLICK TO LEARN MORE ABOUT THE PRESCOTT
Address: 88 Duporth Ave, Maroochydore
Apartments: An ultra-luxury collection of 15 half and full-floor penthouse-style residences.
Builder: Mosaic Construction
Sales Status: SOLD OUT
June was a mammoth month for Mosaic Construction, with the team completing concrete slab pours for levels 6 and 7, permanent power established in the building and the recreational ground floor structures advancing to schedule. Looking ahead, the team will start formwork to Lorient’s roof structure – meaning the official top out of this spectacular collection of homes is close by. July will also see the beginning of joinery fit-outs, the first coat of paint applied to walls and ceilings and finalising preparation for flooring installation.
CLICK TO LEARN MORE ABOUT LORIENT
Address: 7 Douglas Street, Kirra
Apartments: 31
Builder: Mosaic Construction
Sales Status: SOLD OUT
Excitingly, Mosaic Construction is planning to pour the level 4 slab, the midway point for Luca’s structure, after completing level 3 in June. As Luca continues to ascend, the team are kicking off more detailed internal works to the lower levels, starting with waterproofing to glazing openings on level 1. The application of shotcrete to the basement walls will also be finalised, along with installing ceiling sprinkler pipes.
CLICK TO LEARN MORE ABOUT LUCA
Address: Peerless Ave, Mermaid Beach
Apartments: 86
Builder: Hutchinson Builders
Sales Status: SOLD OUT
Dawn has officially reached building top-out, one of the most exciting and significant milestones in any building program. Hutchinson Builders continue to make strong progress, focusing on residential interiors, common areas and recreational spaces. July will see Hutchinson’s target to complete solar panel and glazing installation.
CLICK TO LEARN MORE ABOUT DAWN
Address: 29 Finney Road, Indooroopilly
Apartments: 141 over two boutique buildings
Builder: Mosaic Construction
Sales Status: SOLD OUT
Last month, Mosaic Construction completed the mammoth task of forming and pouring Witton One’s levels 4 and 5 slabs. The team are targeting to complete the level 6 slab pour and prep the level 7 pour this month. Excitingly, Witton Two’s building program will soon commence, following the team aiming to move their site accommodation to Witton One’s basement in July.
CLICK TO LEARN MORE ABOUT THE WITTON
Address: 4 First Ave, Burleigh Heads
Apartments: 34 2 – and 3-bedroom apartments and sub-penthouses over 13 levels
Builder: Mosaic Construction
Sales Status: SOLD OUT
July is another big month for Augusta, with Mosaic Construction approaching the halfway mark of the building structure. Services installation continues unimpeded in the basement, while shotcrete application to the walls is anticipated to be finalised this month. In other great news, waterproofing works have also commenced to the basement 2 stormwater tank and the site’s perimeter blockwork walls are now complete.
CLICK TO LEARN MORE ABOUT AUGUSTA
Address: 42 The Esplanade, Burleigh Heads
Apartments: 9 full-floor Masterpiece Series residences over 9 levels
Builder: Mosaic Construction
Sales Status: SOLD OUT
Florence has begun its above-ground ascent, with scaffold installation commenced last month. July is another big month of concrete slab pours for the team who aim to complete levels 2 and 3. Given Florence and Augusta are adjoining sites, they are being built at the same time. As per above, below ground, shotcreteing to the basement walls is anticipated to be finalised this month with services installation continuing unimpeded.
CLICK TO LEARN MORE ABOUT FLORENCE
Address: 1 Surf Street, Bilinga
Apartments: 13, 3-bedroom Masterpiece Series residences over seven levels
Builder: Mosaic Construction
Sales Status: SOLD OUT
At Bianca, window installation is underway with sewer, water, gas and stormwater connections also finalised. Mosaic Construction continues to make solid progress, looking to complete the level 7 concrete slab pour in anticipation of the official top-out of this spectacular building. Excitedly, interior spaces are starting to come to life, with wall sheeting kicking off to levels 1 and 2, while glazing installation will keep advancing. Energex is also expected to close out the permanent electricity connection in July.
CLICK TO LEARN MORE ABOUT BIANCA
Address: 73 Northcote Street, East Brisbane
Apartments: 81, 2- and 3-bedroom residences over 8 levels
Builder: Mosaic Construction
Sales Status: Only a couple remaining – move quickly.
Mosaic Construction’s bulk excavation reached the bottom basement level in June – meaning the completing of this gruelling task is near. Detailed excavation works will then progress throughout July in preparation for The Mowbray’s first concrete pour. As mentioned in the previous update, the team is also on track to complete the application of shotcrete to the basement walls.
CLICK TO LEARN MORE ABOUT THE MOWBRAY
Address: 146 Surf Parade, Broadbeach
Apartments: 100, 2- and 3-bedroom residences over thirty levels
Builder: Mosaic Construction
Sales Status: Sold Out
June saw a thrilling development in Marella’s construction, with the structure now at ground level and ready to ascend. Marella’s basement slab pour was completed and shotcreting progresses to the basement 1 walls. As the construction program focuses on the month ahead, preparation is underway for Marella’s jump form installation where the team will soon be able to construct multiple floors simultaneously.
CLICK TO LEARN MORE ABOUT MARELLA