It’s been a strong start to 2026 as Mosaic Construction continues to deliver several milestones across our projects. In Brisbane, The Bedford’s basement construction has seen a large-scale construction program kick off, while the height of the tower at The Carter has progressed to Level 6. On the Gold Coast, Isabel reached a defining moment reaching structural top out and marking a defining moment for the building. At Madeline, the excavation of the three-level basement was successfully completed, and Sophia’s basement construction continues to advance at pace. With Lily complete and welcoming first Residents in December 2025, we are now excited to introduce our next project to these regular construction updates, Josephine by Mosaic, located in Burleigh Heads.

Brisbane

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 17 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

January saw the completion of the very first slab‑on‑ground for Basement 4 — a significant achievement that required four sequential pours and enabled the team to begin progressing back up toward ground level. After the lift shaft overrun services were installed, the team moved into a structural program known as the Formwork-Reinforcement-Pour (FRP) cycle. This recurring methodology saw the first two basement levels complete and, weather permitting, the same cycle will continue throughout February, as Mosaic Construction progresses towards Basement 1.

CLICK TO LEARN MORE ABOUT THE BEDFORD

 

The Carter by Mosaic | Kangaroo Point

Address: 73-83 Linton Street, Kangaroo Point

Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: 90% Sold – Act Now

The Carter’s construction progressed steadily as Level 6’s podium concrete slab was poured, and formwork screens were established on Level 7.  Glazing works advanced as waterproofing and subsill installation began on Level 2, while blockwork continued through the lower levels up to Level 4. Throughout February, the tower will keep rising with formwork, reinforcement, and concrete pours across Levels 7 and 8 and the building core is expected to reach Level 12, weather permitting.

CLICK TO LEARN MORE ABOUT THE CARTER

 

 

Gold Coast

Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: SOLD OUT

Isabel reached a major milestone with the tower structure officially topping out, marking the shift from primary structural works to the detailed craftsmanship phase that will define the building’s final form. The benchmark apartment is nearing completion and will guide all future finishes to ensure a consistent, elevated standard. Glazing progressed with Levels 16 and 17 now sealed, enabling internal works to accelerate. This month, roof services and waterproofing begin on Level 19, glazing moves to Level 18, and internal works progress through Levels 3 to 13.

CLICK TO LEARN MORE ABOUT ISABEL

 

 

Madeline by Mosaic | Broadbeach

Address: 22 Mary Avenue, Broadbeach

Apartments: 59, half- and full-floor residences and Sky Homes over 37 levels

Builder: Mosaic Construction

Design Partner: Fraser and Partners

Sales Status: Over 80% Sold

Bulk excavation for the three-level basement of Madeline has been successfully completed, marking a major project milestone. Basement walls are now reinforced with shotcrete, forming a strong structural shell, while essential services progressed with sewer connections and lift pit sheet piles installed. February will bring gantry and site shed installation, along with the arrival of the tower crane—signalling the transition from excavation to vertical construction.

CLICK TO LEARN MORE ABOUT MADELINE

 

 

Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach

Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status:  Now Selling – Limited Opportunities Remaining

At Sophia, bulk excavation advanced to Basement 2 with shotcrete works beginning to stabilise and reinforce the basement walls. The tower crane base has now been poured, and the gantry installed to support safe, efficient site access as activity ramps up. In the coming weeks, construction will accelerate as the project enters a more dynamic phase, highlighted by the arrival and installation of the tower crane, marking the shift toward vertical construction.

CLICK TO LEARN MORE ABOUT SOPHIA

 

Josephine by Mosaic | Burleigh Heads

Address: 166 The Esplanade, Burleigh Heads

Apartments: 30 half- and full-floor residences across 18 levels.

Builder: Mosaic Construction

Design Partner: EMK Architects

Sales Status:  Over Half Sold – Act Now

Josephine has achieved exceptional early momentum, with more than half of all residences sold prior to public release — a milestone driven by early purchasers who believed in the project’s vision. As always, Mosaic Construction, our triple ISO‑certified delivery team, is progressing swiftly through final construction planning. Subject to final approvals, early works — including demolition of the existing building — remain on track to commence in early Q2 2026, giving purchasers continued confidence.