Project updates | 3 minutes

Construction Progress Round-up – February 2025

Mosaic Property
07/02/25

Mosaic Construction has entered the new year with strong momentum, building on a highly successful close to 2024. Following the milestone of welcoming Residents to The Mowbray by Mosaic in January, we have four more projects progressing toward completion the first half of this year. This strong foundation positions us to maintain our positive trajectory throughout 2025, with a continued focus on delivering exceptional results for our customers.

Sunshine Coast

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

Mosaic Construction’s structural top-out of Building 2 (Memorial Avenue) just before the Christmas break set a solid foundation for the next phase of works, with façade installation, soffit rendering, and painting now progressing well.

Another significant milestone to start the year is the commencement of scaffold removal at Building 1 (The Esplanade), offering the first true glimpse of the refined architecture and craftsmanship that will soon welcome Residents.

The scaffold drop for Building 1 is expected to be completed in February, while initial removal will begin at Building 2.

February will also see continued landscaping work take shape while internal work on both buildings will progress.

CLICK TO LEARN MORE ABOUT COTTON TREE

Brisbane

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: SOLD OUT

Mosaic Construction has now reached Level 21, the final residential floor of the structure. The first slab pour is complete, with the second set to follow imminently. Next, attention will turn to structural top-out, paving the way for The Manning’s crowning rooftop recreational spaces to take shape.

Internally, progress continues at a strong pace. High-level services installation has now reached Levels 16 and 17, while window installations are advancing on Levels 15 and 16 which will continue throughout February.

CLICK TO LEARN MORE ABOUT THE MANNING

The Prescott by Mosaic | Toowong

Address: 28 Lissner Street, Toowong

Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels

Builder: Mosaic Construction

Design Partner: DKO

Sales Status: SOLD OUT

The Prescott’s striking façade continues to emerge as scaffold removal progresses. Interior fit-outs are complete up to Level 9, with these residences now secured in preparation for pre-settlement inspections. By the end of this month, Mosaic Construction expects to have all residences up to Level 12 finished and locked up.

Looking ahead, scaffolding will be reduced to approximately Level 4 by the end of the month, weather permitting. Meanwhile, the lobby will begin its transformation into a finished space, stormwater connections will progress, and external works—including footpaths and landscaping—will further define the streetscape.

CLICK TO LEARN MORE ABOUT THE PRESCOTT

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 16 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Now Selling – Act Now

Having received Development Approval (DA) for our minor change application from the Brisbane City Council, the stage is now set for the next exciting chapter as we prepare to commence construction.

At this stage, Mosaic Construction anticipates commencing piling works between late February and early March, pending final approvals from Brisbane City Council and Transurban.

Piling is one of the first steps in construction, followed by basement excavation.

Having received Development Approval (DA) for a minor change application from the Brisbane City Council, Mosaic Construction anticipates commencing piling works between late February and early March, pending final approvals from Brisbane City Council and Transurban.

Following this,  the team will begin basement excavation, marking a pivotal point as we bring The Bedford to life.

CLICK TO LEARN MORE ABOUT THE BEDFORD

Gold Coast

Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: NEAR SELLOUT  – ACT NOW

The installation of the street-front gantry late last year paved the way for major structural progress, including the completion of the Basement 1 staircase blockwork and ongoing shotcreting of the basement ramp walls.

Work is advancing on the Ground Level concrete slab preparation, which is set to be poured in the coming weeks, weather permitting.

Soon after, formwork for the Level 2 deck will take shape, along with the first vertical structures connecting the tower’s lower levels. From here, expect to see rapid progress as Isabel begins its upward rise.

CLICK TO LEARN MORE ABOUT ISABEL

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: SOLD OUT

Lily’s structure has reached Level 22, while the jump form is at Level 25. Window installation continues to move steadily, with glazing now in place up to Level 18 and external painting advancing to Level 19.

Internally, wall framing has reached Level 15, sheeting is underway on Level 14, and painting is progressing to Level 12. Tiling is taking shape on Level 9, and joinery installation is well underway on Level 6.

Weather permitting, Mosaic Construction anticipates reaching Level 25 of the tower this month and advancing the jump form to Level 28, bringing the monumental milestone of structural top-out within sight.

CLICK TO LEARN MORE ABOUT LILY

Marella by Mosaic | Broadbeach

Address: 146 Surf Parade, Broadbeach

Apartments: 100, 2- and 3-bedroom residences over thirty levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: SOLD OUT

As settlement approaches, Mosaic Construction remains focused on finalising ground-floor landscaping, completing the recreational amenities and common areas, wrapping up internal finishing works, and addressing external touch-ups.

We are excited to welcome Residents home from the end of February.

CLICK TO LEARN MORE ABOUT MARELLA

Register for Our Latest Releases