Construction Progress Round-up – August 2025

With the second half of the year now underway, construction progress across our portfolio remains clearly on show. In Maroochydore, Cotton Tree by Mosaic has officially reached completion, while The Manning in Milton is entering its final weeks on site. Isabel by Mosaic continues its upward trajectory above Burleigh Heads, and piling is advancing steadily at Sophia by Mosaic in Palm Beach. Across every location, structural progress and site evolution are moving swiftly as we work towards key delivery milestones.

Brisbane

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: SOLD OUT

Now in the final stage, Mosaic Construction remains dedicated to completing the last finishing touches as we prepare to welcome Residents to their new homes. The Manning is looking wonderful, and we’re immensely proud to soon introduce it as our latest contribution to Brisbane’s dynamic and evolving urban landscape.

CLICK TO LEARN MORE ABOUT THE MANNING

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 16 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 90% Sold – Act Now

Energy on-site remains high as Mosaic Construction powers ahead with major structural works and continues to reach key milestones below ground. In July, the capping beam and retention braces — critical elements that stabilise the excavation and support the future basement — were completed on target, while bulk excavation is advancing to schedule. August will see Mosaic Construction continue with bulk excavation, shotcrete, and infrastructure works.

CLICK TO LEARN MORE ABOUT THE BEDFORD

The Carter by Mosaic | Kangaroo Point

Address: 73-83 Linton Street, Kangaroo Point

Apartments: 125, 2- & 3-bedroom residences & sky homes over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Over 85% Sold – Act Now

The Carter is moving quickly with major structural works and continues to reach key milestones. The tower crane now stands proud above the site and the building’s deep foundations – including piling, strip footings, and pile caps – are now complete. In another significant achievement, the lift and stair core are now in place, while precast concrete walls have been installed. Looking ahead, weather permitting, August will see Mosaic Construction commence stormwater and sewer works, construction of the irrigation tank, and formwork for the suspended ground-level deck. Another significant milestone will see the ground-level slab poured — paving the way for vertical construction in the months ahead.

CLICK TO LEARN MORE ABOUT THE CARTER

Gold Coast

Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: NEAR SELLOUT  – ACT NOW

The team’s primary focus remains on advancing the tower structure which saw concrete works continue and successful pours of the Level 6 and 7 sabs. Glazing installation also commenced between Level 2 and 3, offering a first glimpse of the light-filled interiors beginning to take shape. Looking ahead, August will see Isabel continue its upward momentum with the Level 8 and 9 slab pours targeted. A key milestone will be the tower crane jump to its full height — marking a striking new presence on the Burleigh Heads skyline.

CLICK TO LEARN MORE ABOUT ISABEL

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: SOLD OUT

July delivered another exciting month with the removal of perimeter formwork screens revealing Lily’s full silhouette — a striking architectural statement now proudly visible on the Broadbeach skyline. At rooftop level, both waterproofing and solar panel installations were completed. Internally, window installation is now complete up to Level 32, while party walls and apartment framing have reached Level 31. Residences up to Level 16 are now locked up, defected, and advancing through the next stage of quality assurance. Looking ahead, August will see the momentum continue, with internal fit-out works pushing through the upper levels.

CLICK TO LEARN MORE ABOUT LILY

Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach

Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status:  Now Selling – Register for Exclusive Access

Piling works to install Sophia’s deep structural foundations around the perimeter continue and will carry through to September. Construction of the seawall also commenced on schedule and will continue throughout August. This month will see the connection of external stormwater, sewer, and town water services from the Gold Coast Highway into the site. These connections will establish the essential infrastructure needed to manage water during construction and support integration of the building’s permanent plumbing systems.