Construction Progress Round-up – May 2025

Mosaic Property
06/05/25

From early works to final finishes, Mosaic Construction made strong progress across all sites throughout April. With demolition underway at Sophia, piling in progress at The Bedford, and scaffold coming down at The Manning, each project is moving confidently toward its next major milestone. Here’s a snapshot of the latest activity across the Mosaic portfolio.

Sunshine Coast

Cotton Tree by Mosaic | Cotton Tree

Address: 17 The Esplanade, Cotton Tree

Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status: SOLD OUT

Exciting progress continues at Cotton Tree as both buildings edge closer to completion. In Building 1, final cleans are complete from Levels 1 to 6, defecting has started on Level 8, and works to the swimming pool are now underway. May will see defecting on Level 7 and continued pool construction.

At Building 2, wet area tiling and joinery are now complete on Level 8, with timber flooring and stone benchtops finished on Level 7. Final painting, cleaning, and defecting continue on the lower levels, while basement works — including line marking and bike rack installation — are also progressing.

CLICK TO LEARN MORE ABOUT COTTON TREE

 

 

Brisbane

The Manning by Mosaic | Milton

Address: 33 Railway Tce, Milton

Apartments: 113, 2- and 3-bedroom apartments over 22 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: SOLD OUT

The Manning has entered an exciting new chapter, with scaffold removal now revealing its timeless architectural form and marking a major milestone in the journey to completion.

April saw strong progress across both internal and external works, with joinery now complete to Level 11 and interior fit-out continuing steadily through the upper floors.

Externally, façade painting and landscaping preparation are well underway, adding definition to the building’s emerging presence.

May will see interior works climb higher, and the streetscape take further shape as final detailing continues.

CLICK TO LEARN MORE ABOUT THE MANNING

The Bedford by Mosaic | Kangaroo Point

Address: 16-30 Prospect Street, Kangaroo Point

Apartments: 128, 2- and 3-bedroom apartments and penthouse-style Skyhomes over 16 levels

Builder: Mosaic Construction

Design Partner: BDA Architecture

Sales Status: Now Selling – Act Now

Progress continues to build at The Bedford, with piling now officially underway — a major milestone in establishing the building’s structural foundations.

With two rigs in operation, reinforced concrete piles are being installed around the site perimeter to support the future structure. April saw steady site activity, and weather permitting, piling is expected to wrap up in early June. This will make way for the next key milestone: basement excavation, marking another exciting step forward.

CLICK TO LEARN MORE ABOUT THE BEDFORD

 

Gold Coast

Isabel by Mosaic | Burleigh Heads

Address: 96 The Esplanade, Burleigh Heads

Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.

Builder: Mosaic Construction

Design Partner: Koichi Takada Architects

Sales Status: NEAR SELLOUT  – ACT NOW

Construction at Isabel is moving ahead with strong momentum, with the Level 2 podium slab now complete and the first façade panels installed.

April also saw lift and stair core walls progress to Level 3, and scaffolding erected to support upper-level works.

In May, focus shifts to forming the Level 3 and 4 slabs, along with continued core and façade installation.

CLICK TO LEARN MORE ABOUT ISABEL

Lily by Mosaic | Broadbeach

Address: 4 Rosewood Avenue, Broadbeach

Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels

Builder: Mosaic Construction

Design Partner: Plus Architecture

Sales Status: SOLD OUT

April was another strong month at Lily, with structural works now complete to Level 29 and the jumpform pushing through to Level 33.

Window installation has reached Level 26, while tiling, joinery, and timber flooring continue steadily up the building.

Residences up to Level 4 are now finished and locked up, with quality audits commencing.

In May, the team is targeting structural completion to Level 32, with internal finishes set to reach Level 8.

CLICK TO LEARN MORE ABOUT LILY

Sophia by Mosaic | Palm Beach

Address: 1357 Gold Coast Highway, Palm Beach

Apartments: 32 beautifully appointed 2- and 3-bedroom residences, sub-penthouses, and penthouses over nine levels.

Builder: Mosaic Construction

Design Partner: Bureau Proberts

Sales Status:  Now Selling – Register for Exclusive Access

May marks an exciting milestone at Sophia, with demolition now well underway and progressing steadily onsite.

This will continue over the coming weeks, clearing the way for site establishment and preparations for basement excavation.

Piling remains on track to commence in June, forming the deep structural foundations needed to support the next stage of construction.