The positive charge into the second half of 2024 continues, with notable advancements across our various South East Queensland construction sites. We were on the cusp of several significant milestones, including commencing scaffold removal, achieving structural top-out, and preparing for another Mosaic crane to grace the Gold Coast skyline.
Address: 17 The Esplanade, Cotton Tree
Apartments: Two boutique buildings featuring 8 full-floor, ultra-luxurious 3-bedroom residences and 33 spacious 2- and 3-bedroom residences.
Builder: Mosaic Construction
Design Partner: Bureau Proberts
Sales Status: SOLD OUT
July saw Mosaic Construction achieve the Level 6 concrete slab pour for Building 1 (The Esplanade) and the Level 2 pour for Building 2 (Memorial Avenue).
Additionally, in Building 1 (The Esplanade), windows were installed up to Level 4, and walls and ceilings were sheeted to Levels 1 and 2. The team targets the Level 7 concrete slab pour for Building 1, putting Cotton Tree on the home stretch to structural top-out.
CLICK TO LEARN MORE ABOUT COTTON TREE
Address: 33 Railway Tce, Milton
Apartments: 113, 2- and 3-bedroom apartments over 22 levels
Builder: Mosaic Construction
Design Partner: BDA Architecture
Sales Status: NEAR SELLOUT – ACT FAST
Mosaic Construction achieved four major concrete pours in July, with the latest being the second of two for Level 9. This milestone puts The Manning on the exciting home stretch toward the structural halfway point.
Detailed interior work will commence once The Manning reaches the designated height. For now, the priority continues to be advancing the tower’s construction which is tracking to schedule.
CLICK TO LEARN MORE ABOUT THE MANNING
Address: 28 Lissner Street, Toowong
Apartments: 101, 2- and 3-bedroom apartments and Masterpiece Skyhomes over 14 levels
Builder: Mosaic Construction
Design Partner: DKO
Sales Status: SOLD OUT
Mosaic Construction achieved four significant concrete pours in July, the latest being the first of two for Level 11, bringing The Prescott into the thrilling final stages towards structural top-out.
Meanwhile, wall and ceiling framing has reached Level 4, with wall sheeting following right behind at Level 3, and high-level services are closed out to Level 6.
CLICK TO LEARN MORE ABOUT THE PRESCOTT
Address: 73 Northcote Street, East Brisbane
Apartments: 81, 2- and 3-bedroom residences over 8 levels
Builder: Mosaic Construction
Design Partner: DKO Architecture
Sales Status: SOLD OUT
Mosaic Construction is advancing wall sheeting, setting, and sanding to Level 8, with all other levels closed out.
The first interior paint application remains on schedule, and tiling is progressing through Levels 5 to 7. Externally, render works are at the upper levels, and the rooftop pool shell has been poured.
August marks a massively exciting milestone as, weather permitting, we begin the highly anticipated task of progressively removing the scaffold from The Mowbray’s top levels down. This significant step not only reveals the building’s final beauty but also signifies that we are entering the final phases of construction.
CLICK TO LEARN MORE ABOUT THE MOWBRAY
Address: 96 The Esplanade, Burleigh Heads
Apartments: 28 half and full-floor residences and Sky Homes across 16 levels and two split-level penthouses, each with private pool.
Builder: Mosaic Construction
Design Partner: Koichi Takada Architects
Sales Status: NEAR SELLOUTÂ – ACT NOW
Mosaic Construction is poised to achieve a significant milestone with the imminent completion of Isabel’s basement excavation.
Shotcreting, which involves spraying concrete onto surfaces at high velocity, is progressing on the basement walls. Meanwhile, the team is trimming the piles initially driven into the ground around the site’s perimeter for essential structural support to prepare for the next construction phase.
CLICK TO LEARN MORE ABOUT ISABEL
Address: 4 Rosewood Avenue, Broadbeach
Apartments: 98, 2- and 3-bedroom residences and Sky Homes over 29 levels
Builder: Mosaic Construction
Design Partner: Plus Architecture
Sales Status: SOLD OUT
In July, the team successfully completed the Level 4 and Level 5 concrete slab pours, prepared for the Level 6 pour and advanced the jump form to Level 9. Window installation is also progressing on the lowest levels.
Most excitingly, internal works will commence this month as Mosaic Construction begins forming Lily’s Residences. This will kick off with wall and ceiling framing.
CLICK TO LEARN MORE ABOUT LILY
Address: 146 Surf Parade, Broadbeach
Apartments: 100, 2- and 3-bedroom residences over thirty levels
Builder: Mosaic Construction
Design Partner: Plus Architecture
Sales Status: SOLD OUT
Mosaic Construction is making outstanding strides and is now, remarkably, on the cusp of Marella’s structural top-out, well ahead of its anticipated schedule thanks to exceptional programming and execution by the site team.
August has Mosaic Construction targeting a massively exciting milestone, Marella’s structural top out, and dismantling and removing the jump form.